LAUREL ENVIRONMENTAL ASSOCIATES, LTD.

53 West Hills Road,
Huntington Station, NY 11746

(800) 453-0578


Phase I Environmental Site Assessments
Written Report of Findings

A Phase I Environmental Site Assessment (ESA) consists of four main components:


Once Laurel completes the site history review, a site-specific environmental study, and review of federal, state, and local databases the compiled information is prepared into a final report for the client. The report includes pertinent information regarding the Subject Property and related on-site operations, as well as identifying current and historical environmental impacts of surrounding properties, up to a one-mile radius.

The final report includes the appropriate attachments and appendices to provide a comprehensive review of the site. By conducting environmental due diligence with respect to the site, recommendations are provided to the client regarding next steps for any necessary remedial actions to take place at the Subject Property. Should any sampling or remediation need to be conducted at the site, Laurel is a full-service consulting firm with the means and expertise to proceed on to Phase II or Phase III work.

After the completion of the final Phase I Environmental Site Assessment, Laurel has acquired all essential background information regarding the site to be able to move forward with certainty. Ultimately, this full-service capability allows Laurel to stand out with distinction from the competition to better serve our clients.

Click here to go back to Phase I Main Page

Services Include:

Site History Review

determine what hazardous substances may have been present

review of federal, state and local databases

determine if the subject site or any sites up to a one mile radius of the subject site are listed

A site specific study

of the pertinent geologic, hydrogeologic conditions and hydrologic data found at the site

Written report of findings

 clearly lay the groundwork for additional study, if warranted.

If contamination is discovered, LAUREL can design and optimize an economical mitigation plan that is environmentally sound.  In some cases, early implementation of a proactive remedial strategy will permit a property transaction to move forward while a clean-up is in progress.

Phase II Soil / Groundwater Testing

When there is suspicion of contaminated soil or contaminated groundwater at a site, sampling and analysis must be completed to confirm the presence or absence of the suspected contaminants.  This is achieved through the installation of groundwater monitoring wells and sampling of soil from cores.

The validity of the results obtained through this sampling relies heavily on the proper placement of monitoring wells and soil borings, though the placement is largely subjective.  It is therefore important for a highly skilled scientist to conduct research on site history and visual reconnaissance in formulating a plan, and final decision of proper placement of the monitoring wells and borings to obtain relevant samples.


Whenever possible, LAUREL makes every effort to limit costs, damage to property and especially disruption of business, through the use of the latest state of the art drilling and sampling equipment available.

 DATA COLLECTION

Correct media sampling methods are just as important as proper well installations and sampling point decisions.  Utilizing the correct sampling equipment and decontamination techniques, LAUREL ensures that no cross contamination has occurred. Without exception, only properly trained and certified staff collect samples.

SOIL BORINGS AND MONITORING WELL INSTALLATIONS

When there is suspicion of contaminated soil or contaminated groundwater at a site, sampling and analysis must be completed to confirm the presence or absence of the suspected contaminants.  This is achieved through the installation of groundwater monitoring wells and sampling of soil from cores.

 

GROUNDWATER/SOIL SAMPLING AND ANALYSIS

Groundwater depths and product thicknesses are determined using an oil/water interface probe.  Wells are developed using a bladder pump, to a turbidity (a measure of the silt present in water) of 50 nephelometric units (NTU's), or less to ensure proper hydraulic connection with the surrounding aquifer.

DRINKING WATER SAMPLING AND ANALYSIS

Lorem ipsum dolor sit amet, at duo affert homero incorrupte, vis eripuit accusata ut, wisi reprehendunt cum in. Te facete accumsan quo. Simul dolor eos te, ad possit adipiscing pri.

SLUDGE
SAMPLING 

 LAUREL has found that septic systems, and industrial and storm water leaching pools are often receptors of significant contamination at any given property.  By design, these systems leach as much water as possible into the ground.

 GEOPHYSICAL SURVEYS

LAUREL conducts geophysical surveys to aid in the discovery of underground storage tanks, buried drums, fill material, unexposed drywells and large scale subsurface hydrocarbon contamination with no excavation or drilling necessary.

BROWNFIELD REDEVELOPMENT

When there is suspicion of contaminated soil or contaminated groundwater at a site, sampling and analysis must be completed to confirm the presence or absence of the suspected contaminants.  This is achieved through the installation of groundwater monitoring wells and sampling of soil from cores.

The validity of the results obtained through this sampling relies heavily on the proper placement of monitoring wells and soil borings, though the placement is largely subjective.  It is therefore important for a highly skilled scientist to conduct research on site history and visual reconnaissance in formulating a plan, and final decision of proper placement of the monitoring wells and borings to obtain relevant samples.


Whenever possible, LAUREL makes every effort to limit costs, damage to property and especially disruption of business, through the use of the latest state of the art drilling and sampling equipment available.

 

MORE ENVIRONMENTAL SERVICES

Indoor Air Quality Studies

Soil / Groundwater Remediation

Brownfield Redevelopment

Tank Removal, Installation, Testing, Design and Permitting

Underground Injection Control (UIC) Program

Lead and Asbestos Testing and Operations and Maintenance (O & M) Programs

Contact Us

 

631-673-0612

 

53 West Hills Rd, Huntington Station, NY, 11746

Find us on Facebook

© 2019 Laurel Environmental Geosciences D.P.C.